MACTEC’s Route 54 EA Honored by
ACEC
MACTEC's Environmental Assessment for
Missouri Route 54 has received an Honor
Award from ACEC/Missouri. The award recognizes
excellence in performing significant projects.
The St. Louis office completed the route
location study and environmental assessment
for a two-mile section of new four-lane
divided freeway through the heavily developed
Lake of the Ozarks area. Heading the effort
were Ray Steege, Project Director, and
Steve Coates, Project Manager. Lois DuMey
and Christie DuMey handled the environmental
and socioeconomic assessment tasks, and
Brian Mueller did the GIS work. Rich Hart
and Greg Jolly performed GeoPak and CADD
design, and Jeff Strickland ran a highly
successful public involvement program.
The 24-month study performed for the Missouri
Department of Transportation (MoDOT) Central
District required numerous alternative
routing and interchange concepts to minimize
impacts to land use and the environment
and to gain public acceptance.
Regional traffic congestion led MoDOT
to seek a way to accommodate increasing
numbers of vehicles using a single road
corridor in rugged terrain with steep hillsides.
After studying various approaches, MACTEC,
assisted by traffic consultant Crawford
Bunte Brammeier, determined that building
a road on a new alignment was preferable
to upgrading the existing roadway or trying
to manage traffic with signals and rerouting
vehicles.
Working closely with MoDOT Central District
staff, MACTEC devised an innovative one-way
couple interchange design for the highly
congested south end of the corridor. This
design featured a split diamond interchange
with a companion one-way road to produce
continuity and safety by dividing east-
and west-bound traffic onto separate one-way
roads joined by one-way collector ramps.
On-and off-ramps complete the interchange
at the ends of the diamond.
Opposition to the original alternative
for the new Route 54 freeway was particularly
vocal among condominium residents (507
signed a petition against the proposal).
Another contentious issue was the unconventional
one-way couple interchange. An extensive
public involvement program helped allay
concerns. Public meetings at key locations
in the prospective corridor were frequently
held. One meeting was devoted to the concerns
of the condominium development that was
the center of opposition to the original
plan. Using VISSIM simulation software,
the study team graphically demonstrated
the traffic situation and the effects various
alternative approaches would have on traffic.
High quality static displays created by
Geographic Information Systems (GIS) software
helped document the respective noise and
congestion reduction impacts of the alternatives.
Results exceeded client expectations by
bringing the report in $200,000 below budget.
Budgeted cost was $790,000, and actual
cost was $550,000, a measure of effective
project management. The team met its delivery
schedule of early 2004 by delivering its
final report on May 4, 2004.
The Route 54 Environmental Assessment
and Location Study provides the groundwork
for roadway improvements that will reduce
traffic congestion, improve safety and
allow sustainable community development
by creating a new roadway while preserving
the existing facility as a local road.
|