MACTEC Projects
MACTEC  

Centric Software

“…CE is very happy with the entire MACTEC organization from the personal attention we have received… Due to this service, CE considers MACTEC to be a partner, not just a vendor, when it comes to solving all of CE’s long term environmental issues…”

Environmental Engineering Manager, Combustion Engineering

Featured Projects

ABB, Inc.

Closure and Redevelopment of Inactive Manufacturing Facility (1993 – 2003)

To assist ABB, Inc. in redeveloping a former instrument manufacturing facility in Rochester, New York, MACTEC provided a full range of environmental services during all project phases including initial site assessment and investigation, remedy evaluations and selections, interim remedial actions, pilot testing, regulatory negotiations, remedial planning and design, and remediation. The facility had a 90-year history of manufacturing operations involving mercury, solvents, electroplating chemicals, and other materials.

The project won the Consulting Engineers of Tennessee Runner-up Award in 1999 and is one of the largest and most visible projects conducted under New York’s Voluntary Cleanup Program.

MACTEC’s services included feasibility studies, risk assessment, asbestos abatement, storm sewer rehabilitation, underground storage tank removal, facility demolition, and comprehensive groundwater, soil, and waste characterization. We also provided full-scale operation and maintenance for a dual-phase vacuum extraction remediation system for groundwater that had been contaminated with volatile organic compounds.

Project highlights included...

  • A $4 million facility demolition effort was completed on schedule in 9 months and within 90% of the original budget estimate.
      
  • A $5 million remedial effort for mercury-contaminated soil and trichloroethylene-contaminated soil and groundwater was completed on schedule in 9 months and within 90% of the budget estimate.
      
  • MACTEC helped the client save millions of dollars in waste handling and disposal costs by working with environmental attorneys to establish that the majority of mercury-bearing demolition and excavation wastes would be treated not as a listed hazardous waste, but according to whether it exhibited hazardous characteristics. Despite initial opposition from the regulatory agency, the project team’s technical arguments, based on RCRA interpretation and case law precedent, were eventually accepted.

Nuclear Fuel Facility Decommissioning and Demolition (2001–05)

MACTEC performed D&D of the former nuclear fuel fabrication facilities in Windsor, Connecticut to obtain unrestricted release from the NRC and reduce ABB’s long-term liability. Work on the 600-acre site included characterization, radiological decontamination, asbestos and lead abatement, above- and below-grade demolition, site restoration, and waste management (radiological, hazardous, and mixed) including packaging, segregation, sizing, and shipping.

MACTEC’s activities included...

  • D&D of 10 nuclear fuel fabrication facilities totaling approximately 200,000 square feet and encompassing 30 acres
  • Characterization of land using MARSSIM-based survey
  • Characterization of structures, soils, and groundwater
  • Waste minimization including decontamination
  • Hazardous materials removal
  • Structural dismantlement and demolition
  • Slab and underground utility removal
  • Utility modifications and isolations
  • Soil remediation
  • Groundwater monitoring well installation, and sampling and analysis for chemical and radiological constituents
  • Groundwater modeling, and fate and transport evaluation
  • NRC license support (amendments, decommissioning plan, etc.)
  • Final status survey for NRC approval