|

Refuse Incinerator
Lajes Field, Azores
MACTEC performed a value engineering study for this 25 ton per day refuse incinerator plant. The project included the building, trash storage, site improvements and incineration equipment. The construction cost for this project was $2.3 million plus an additive bid item of $811,000. The team generated 18 ideas and developed 10 for consideration by the design team. A total of construction cost savings of $675,000 was realized as the result of the VE effort.
|